Express Completes New Seattle Restaurant
Seattle - Express Construction Company recently completed
major tenant improvements to Union, a new restaurant located
in the Poll Building at the corner of First Avenue and Union
Street.
Working under a strict budget and on a tight five-week timeline
to meet a scheduled opening, Express renovated the 4,069-sq.-ft.
space into the modern, new downtown restaurant. The space
features radius walls, hardwood flooring, custom-designed
casework with glass-lighted tops and other high-quality accents.
Tom Bennett, project manager, and Chris Hashbarger, superintendent,
led the project for Express, and Henry Walters with Walker
Architecture provided design services. Other project team
members included David McCauley Floors, Generation Glass,
Northwest Woodworks, and Wizard Electric.
Former DT Architecture Creates New Firm
Seattle - DT Architecture recently transitioned to a new
firm - MOSAIC - Architecture, Planning and Design. This event
signifies a change in ownership structure and a renewed commitment
to design excellence, community planning and service. Joshua
Scott has worked in Seattle for DT Architecture since September
2000, and will continue as principal of MOSAIC's Seattle studio.
DT Architecture's past and current clients will continue to
receive design and planning services from the MOSAIC's studio,
located at 3131 Western Ave.
MOSAIC is the collaboration between two studios, located
in Helena, Mont., and Seattle. Significant completed public
projects by the former DT Architecture include the Great Northern
Town Center in Helena, Mont., the University of Montana Student
Recreation Center, and the remodel of the High Point Shopping
Center in Port Orchard, Wash.
RCIE Awarded $9.2 Million Contract
Hanford - RCI Environmental was recently awarded the $9.2
million contract for the construction of Environmental Restoration
Disposal Facility Cells 5 & 6.
The Environmental Restoration Disposal Facility (ERDF) is
a large CERCLA disposal facility that receives radioactive
and chemically contaminated wastes from the Hanford site.
The facility currently consists of four disposal cells. RCIE's
contract is to expand the facility to six cells. Each cell
is approximately 50 ft. by 500 ft. at the base and 70 ft.
deep. At the surface, each pair of cells is approximately
710 ft. by 1410 ft. The cells have a double liner, double
leachate collection system, and some ancillary site work.
The leachate collection system includes construction of one
crest pad building for each cell housing a piping manifold
and electrical controls, and instrumentation for the cell's
three submersible pumps (a total of six submersible pumps).
Also included is the piping between the manifolds and sumps
at the bottom of the cells, extension of double lined piping
from the new crest pad buildings to the existing leachate
collection system, and extension of the existing electrical
power and signal wires to the new crest pad buildings.
Earthwork will consist of excavating approximately 1.2 million
bank cubic yards of soil, most of which will be placed in
a nearby stockpile. Approximately 140,000 bcy of the excavated
soil will be compacted at the edge of the excavation to form
embankments for the new cells. A pug mill will be operated
to produce approximately 75,000 cubic yard of bentenite clay/soil
admix. A three-foot thick operations layer of excavated soil
will be placed on top of the completed liner system.
The liner system will consist of the admix layer, two one-foot
thick gravel drainage layers, and two high-density polyethylene
(HDPE) liners with associated geotextile and geomembrane layers.
Ancillary site work will include addition of yard lighting
and piping in the nearby waste transportation container queue
area.
Southview Center Two Complete by
April
Vancouver - Team Construction of Vancouver, Wash., was recently
selected to build Southview Center Two, a new office complex
located at 3250 SE 164th Ave. here.
The new 23,269-sq.-ft. center will feature steel frame construction
with a brick veneer finish. Interior spaces will be fashioned
to accommodate new tenants and a 100-car parking lot. New
concrete walkways will highlight the supporting exterior finishes.
Construction is expected to be complete in April.
|